Kearney Sq Bridge Work

Public Road/Construction Projects Update: Week of March 3 – March 9 March 1, 2013
Note:  All work is subject to weather conditions.Information provided by project managers and current as of distribution date.

Kearney Square Bridge replacement

• Beginning Tuesday, March 5 work will begin with installation of traffic control devices and other activity in preparation for reconstruction

• This project is expected to take 6 months and be completed by the end of August

• Construction will be done in two phases with two lanes of traffic and a sidewalk maintained throughout

• Traffic lanes will be narrow (9’ in each direction) but passable; care should be exercised when traveling through this area

• This project is being done by Boott Hydropower, Inc., a subsidiary of Enel Green Power North America, Inc.

• A construction informational meeting will be held on March 11, 2013 at 7 PM at Middlesex Community College

• For questions/comments please contact KearneySquareBridge@Enel.com